Bridge Building [2. Post-Construction Phase]
Phase I
5. Layout for bridge foundation
6. Bridge foundation excavation
7. Stone Dressing work at the bridge site
8. Dry stone masonry wall of bridge foundation
Phase II
9. Handing over of const. materials to UC at road
11. Briefing on bridge parts to Community
 
10. Cable Transportation from road head to bridge site
Phase III
12. Cement Stone masonry tower construction
13. Concreting work
14. Cable Pulling at bridge site
15. Completion of cable pulling
16. Walkway erection
17. View of completed bridge